Crusoe 放弃 12.5 亿美元 Boom 涡轮机采购计划

Crusoe abandons $1.25B plan to use Boom turbines at AI data centers

摘要Summary

丹佛 AI 数据中心初创公司 Crusoe 终止了向 Boom Supersonic 采购 29 台 42 兆瓦 Superpower 天然气涡轮机的 12.5 亿美元协议,该协议原本是其新业务的启动订单。Crusoe 表示能源计划未变,仍将使用涡轮机,只是不再选择 Boom,这对刚融资 3 亿美元、欲以电站业务反哺超音速客机研发的 Boom 构成挫折。

Denver-based AI data center startup Crusoe has ended its $1.25 billion deal to buy 29 of Boom Supersonic's 42-megawatt Superpower natural gas turbines, a contract that had made it the launch customer for Boom's new stationary power business. Crusoe said its energy plans are unchanged and it still intends to use turbines, just not Boom's, a setback for Boom, which raised $300 million largely to commercialize the business and fund its Overture supersonic jet.

  • Crusoe 终止 12.5 亿美元采购 29 台 Boom 涡轮机协议
  • Crusoe 称仍用涡轮机,但不再选 Boom
  • Boom 称明年交付约 250MW,2028 年目标 1GW

全文对照Full text · 中 / EN

总部位于丹佛的AI数据中心初创公司Crusoe近期融资39亿美元,已终止使用同城公司Boom Supersonic开发的新系列固定式发电厂的计划。

Crusoe, a Denver-based AI data center startup that recently raised $3.9 billion , has ended plans to use a new line of stationary power plants developed by fellow Denver company Boom Supersonic.

Crusoe成立于2018年,最初是一家利用油田多余天然气进行比特币挖矿的公司,此后已成为最大的AI数据中心建设者之一,包括在德克萨斯州阿比林的一个大型园区,为OpenAI提供算力。

Founded in 2018 as a bitcoin miner that ran on excess natural gas from oil fields, Crusoe has since become one of the biggest builders of AI data centers , including a massive campus in Abilene, Texas, that supplies computing power to OpenAI.

Boom Supersonic正在开发名为Overture的超音速客机,去年推出了一项新业务,将其为该客机开发的发动机版本作为天然气固定式发电厂出售。其Superpower涡轮机与名为Symphony的航空发动机共享约80%的相同部件。

Boom Supersonic, which is developing a supersonic passenger jet called Overture, launched a new business last year to sell a version of the engine it’s developing for that jet as natural gas-fired stationary power plants. Its Superpower turbine shares about 80% of the same parts with that airborne engine, called Symphony.

Crusoe曾签约成为该业务的首个客户,同意斥资12.5亿美元购买29台Boom的42兆瓦Superpower涡轮机。首批交付原定于2027年开始。但据Boom Supersonic CEO Blake Scholl称,该交易此后已破裂。

Crusoe had signed on to be the first customer for this business, agreeing to spend $1.25 billion on 29 of Boom’s 42-megawatt Superpower turbines. The first deliveries were supposed to begin in 2027. But that deal has since fallen apart, according to Boom Supersonic CEO Blake Scholl.

周五,在X上的一篇帖子中,Scholl在祝贺Crusoe创始人Cully Cavness和Chase Lochmiller公司近期融资后表示,两家公司不再推进涡轮机发射合作。不过他也指出,其他客户正在其管道中。

On Friday, in a post on X , after congratulating Crusoe founders Cully Cavness and Chase Lochmiller on the company’s recent raise, Scholl said the companies are no longer moving forward with the turbine launch partnership. Although he did note that other customers were in its pipeline.

“Boom明年将向其他站点交付约250MW的Superpower,我们的目标是2028年达到1GW,”Scholl写道。“我们感谢Crusoe在塑造Superpower过程中给予的帮助,并继续为他们的成功喝彩。未来很长,我们期待在涡轮机成为他们主要电力组合的一部分时可能合作。”

“Boom will be delivering about 250MW of Superpowers next year to other sites, and we’re targeting 1GW in 2028,” Schooll wrote. “We’re grateful for the help Crusoe gave us in shaping Superpower and continue cheering for their successes. The future is long, and we look forward to potentially teaming up if/when turbines become part of their primary power mix.”

Scholl最初的帖子包含一句他后来删除的话:“TL/DR是涡轮机不再是Crusoe在阿比林等地近期主要电力组合的一部分,因此发射合作根本不合适。”Crusoe发言人Andrew Schmitt随后告诉我们,该公司的能源计划“没有改变”,仍计划使用涡轮机,“只是不是Boom的”。

Scholl’s initial post include a line which he later removed: “The TL/DR is that turbines are no longer part of Crusoe’s near term primary power mix at Abilene/etc., so a launch partnership just didn’t make sense.” Crusoe spokesperson Andrew Schmitt subsequently told us that the company’s energy plans “haven’t changed” and that it still plans to use turbines, “just not Boom’s.”

Andrew Schmitt 在一封电子邮件中表示:“我们从电力源头开始建设 AI 工厂,并在全国范围内上线新的园区,这些园区由创新能源供电。随着我们的业务组合不断扩大,我们保持灵活性,根据每个站点需求的变化选择适合的能源解决方案——包括涡轮机,以及风能、太阳能、电池和电网。虽然 Boom 一直是一个很好的合作伙伴,但这一合作如今已不再合适。我们祝愿他们一切顺利。”

“We build AI factories from the power up, and we’re bringing new campuses online across the country, powered by innovative energy sources,” Andrew Schmitt said in an email. “As our portfolio grows, we stay flexible, choosing the energy solutions that are right for each site as its needs evolve — including turbines, along with wind, solar, batteries and the grid. While Boom has been a great partner, the partnership isn’t the right fit today. We wish them well.”

据该公司称,Crusoe 在 Abilene 为 Oracle 和 OpenAI 建设的初始 1.2 吉瓦数据中心由电网供电。此外还有一座仅用于备用电源的燃气轮机发电厂。Crusoe 还在 Abilene 为 Microsoft 建设一座 900 兆瓦的数据中心,该数据中心将由现场燃气轮机供电。

Crusoe’s initial 1.2 gigawatt data center in Abilene that was built for Oracle and OpenAI is powered by the grid, according to the company. There is also a gas-turbine power plant that is used for backup power only. Crusoe is also building a 900 megawatt data center in Abilene for Microsoft, which will be powered by on-site gas turbines.

失去其启动客户对 Boom 来说似乎是一次挫折。Boom 去年筹集了 3 亿美元,主要用于将这项新业务商业化。Scholl 当时告诉 TechCrunch,其想法是利用固定式发电厂业务的利润来资助 Overture 的研发。

Losing its launch customer is seemingly a setback for Boom, which raised $300 million last year, largely to commercialize the new business. The idea, Scholl told TechCrunch at the time, was to use profits from the stationary power plant business to fund the development of Overture.

在本文发布前,未能联系到 Scholl 置评;如果他作出回应,TechCrunch 将更新本文。

Scholl could not be reached for comment before publication; TechCrunch will update this article if he responds.