数据中心因电网接入漫长转向改装喷气发动机自发电

Data centers are turning to old jet engines as the wait for power grows

摘要Summary

由于电网接入和新涡轮机交付需等待数年,部分 AI 数据中心开始使用由退役飞机发动机改装而成的天然气发电机组自建电力。xAI、OpenAI 和 Crusoe 等公司已采用此类方案,可将数据中心上线时间缩短至 24 个月,但效率较低且污染更高。

Facing years-long waits for grid connections and new turbines, some AI data centers are generating their own power with converted jet engines burning natural gas. Companies including xAI, OpenAI and Crusoe have adopted the approach, which can get a data center running in 24 months, though the units are less efficient and more polluting.

  • 电网接入需约七年,改装喷气发动机可将数据中心上线缩短至 24 个月
  • xAI 在密西西比安装 8 台改装机组,为 Colossus 2 供电
  • 改装机组效率低、污染高,专家认为可能只是短期方案

全文对照Full text · 中 / EN

据《纽约时报》周二报道,由于并网和新增涡轮机需要排队数年之久,一些人工智能数据中心正利用改装后的喷气发动机自行发电。

Stuck in years-long lines for grid connections and new turbines, some AI data centers are making their own electricity with converted jet engines, the New York Times reported Tuesday.

这些发动机取自退役飞机,经改装后燃烧天然气,并非任何人理想中的永久性发电厂。但它们也再次表明,电力供应已远远落后于人工智能基础设施的建设步伐。

The engines, pulled from retired aircraft and rebuilt to burn natural gas, aren’t anyone’s idea of a permanent power plant. But they’re another sign of how far power supply has fallen behind the AI buildout.

对于困在排队队伍中的企业来说,改装喷气发动机的主要吸引力在于其能够多快投入运行。Rystad Energy 分析师 Audun Martinsen 对《纽约时报》表示:“关键在于尽可能快地获得电力。”他说,借助喷气发动机驱动的机组,“他们可以在 24 个月内让数据中心投入运行”。

For companies stuck in those lines, the main draw of converted jet engines is how quickly the engines can be up and running. “It’s all about getting power as fast as possible,” Rystad Energy analyst Audun Martinsen told the Times. With jet-powered units, “they can have a data center running in 24 months,” he said.

相比之下,根据国际能源署的数据,在弗吉尼亚州北部向电网接入 100 兆瓦电力大约需要七年时间。全球顶尖发电设备制造商之一 Mitsubishi Power 的一位高管上周对 Bloomberg 表示,大部分发电容量预计要到 2031 年才能上线。

Hooking up 100 megawatts to the grid in Northern Virginia, by comparison, takes about seven years , according to the International Energy Agency. Most power capacity is expected to come on by 2031, an executive at Mitsubishi Power, one of the world’s top makers of power generation equipment, told Bloomberg last week .

在某些情况下,这些延迟已经让一些数据中心运营商失去了业务。上个月,在 local utility 表示要到 2030 年代初至中期才能提供足够电力后,Microsoft 退出了作为 Nscale 位于英格兰 Loughton 数据中心锚定客户的角色。

In some cases, these delays are already costing some data center operators business. Last month, Microsoft pulled out as the anchor customer for Nscale’s data center in Loughton, England, after the local utility said it couldn’t deliver enough power until the early to mid-2030s.

据《纽约时报》援引州许可文件和卫星图像报道,Elon Musk 的 xAI 是已经在使用这些发动机的公司之一,该公司在密西西比州安装了八台改装喷气发动机涡轮机,为其位于孟菲斯的 Colossus 2 数据中心提供电力。这些机组来自 ProEnergy,该公司翻新的是常见于 Boeing 喷气式飞机上的 GE 发动机。

Elon Musk’s xAI is among the companies already using the engines, having installed eight converted jet-engine turbines in Mississippi to help power its Colossus 2 data center in Memphis, the Times reported, citing state permits and satellite imagery. The units come from ProEnergy, which rebuilds a GE engine commonly found on Boeing jets.

2025 年,OpenAI 效仿 Musk 的做法,在其位于得克萨斯州 Abilene 的首个 Stargate 站点使用了燃气轮机。总部位于丹佛、建设人工智能数据中心的初创公司 Crusoe 正在建设该 Abilene 园区,并于 4 月订购了 13 台 ProEnergy 的改装机组。

In 2025, OpenAI followed Musk’s lead with gas turbines at its first Stargate site in Abilene, Texas. Crusoe, a Denver-based startup that builds AI data centers, is constructing that Abilene campus and ordered 13 of ProEnergy’s converted units in April.

9月,Crusoe放弃了一项价值12.5亿美元的交易,该交易原本要从Boom Supersonic购买29台天然气涡轮机。Boom Supersonic是一家正在开发超音速客机的初创公司,同时也已开始将该客机发动机的一个版本作为数据中心发电设备出售。Crusoe发言人当时对TechCrunch表示,公司仍计划使用涡轮机。

In September, Crusoe walked away from a $1.25 billion deal to buy 29 natural gas turbines from Boom Supersonic, a startup developing a supersonic passenger jet that has also begun selling a version of that jet’s engine as a power plant for data centers. A Crusoe spokesperson told TechCrunch at the time that the company still plans to use turbines.

目前,特朗普政府正在通过鼓励数据中心自行发电来加大压力。

Currently the Trump administration is adding to the pressure by encouraging data centers to generate their own electricity.

不过,改装喷气发动机也有代价:据《纽约时报》报道,与专为传统天然气发电厂设计的涡轮机相比,它们效率更低、污染更大,而且要达到同样的发电量需要更多台。这可能最终使改装喷气发动机成为一种短期方案,一些专家表示,效率和环境方面的担忧可能在一两年内变得更加重要。

Converted jet engines come with trade-offs, though: They’re less efficient and pollute more than turbines designed for conventional gas plants, and it takes more of them to make the same amount of power, according to the Times. That may ultimately make converted jet engines a short-term play with some experts saying that efficiency and environmental concerns may grow in importance in a year or two.